The Parkway entrance leading to Crest Haven was closed up tight last week as a massive project on the Garden State Parkway continued. The Parkway entrance leading to Crest Haven was closed up tight last week as a massive project on the Garden State Parkway continued. CAPE MAY COURT HOUSE – Work on the Garden State Parkway will lead to several road closures during the coming weeks, when the state Turnpike Authority sets 140-foot beams into place in advance of coming overpasses, a local official said at the Monday, May 19 meeting of the Township Committee.

Committeeman Dan Lockwood met with the authority on Friday, May 16, to discuss several concerns that the committee and area residents have with the project.

As a result of the meeting, the duration traffic signals allowing access to the parkway from Stone Harbor Boulevard will be adjusted. Temporary fencing along the project will also be maintained, and new fencing will be installed by the authority with input from the township and county.

Lockwood also addressed what he called “pinch points on the parkway,” and requested that the authority keep two lanes open at all times.

The setting of the beams, however, will lead to some road closures, said Connie Mahon, township business administrator.

Schedule

* Tuesday, June 3, Crest Haven westbound will be closed, 9 a.m.-2 p.m.

* Wednesday, June 4, Shellbay Avenue westbound will be closed, 9 a.m.-2 p.m.

* Thursday, June 5-6, Stone Harbor Boulevard westbound will be closed, 7 p.m.-5 a.m.

Photos by Bill Barlow

Workers get an overpass ramp prepared last week at the Cape May Court House Parkway exit last week. Workers get an overpass ramp prepared last week at the Cape May Court House Parkway exit last week.